Plans for permanent repairs for A59 at Kex Gill released

/
Please share the news
  • 6
    Shares

Only one week of closure will be necessary during permanent repairs to the A59 at Kex Gill.

North Yorkshire County Council and its contractors told a public meeting in that the work would take eight weeks, but one lane will remain open under traffic light control with just one week of complete closure at the end to allow resurfacing.

The road had to be closed at Kex Gill in late spring after movement was found in the carriageway. After a first phase of repairs, it reopened to single-file traffic under traffic lights in early July. The A59 is an important trans-Pennine route between and , but there is a history of instability in land around the road west of Blubberhouses.

The meeting was told that the permanent repair work will begin on Monday 8 October. It will involve installing ground anchors through to the hillside, constructing a reinforced concrete wall, constructing a filter drain and carriageway resurfacing. The schedule will be subject to weather and ground conditions. It is hoped both lanes will be open to traffic by December.

 

County Councillor , executive member for , said:

We were determined to minimise any road closure while the permanent repairs were carried out. We know how much impact this has on local residents and businesses. Therefore, we are delighted that a road closure is only expected to be necessary at the end of the project for drainage, resurfacing and relining work.

 



 

County Councillor Stanley Lumley, member for the division and a member of the Kex Gill steering group, said:

We are happy that the road will only need to close for one week as this minimises the disruption to the local community. The permanent repairs provide the best solution until a diversion can be finalised.

 

The county council’s ultimate solution is to realign this section of the A59 to the other side of the valley. A preferred route for this realignment was agreed by the council in July and a full business case for funding is being submitted to the Department for Transport. It is hoped construction could start in the spring 2020 and the road could take 14 months to complete.

 



 


Please share the news
  • 6
    Shares

Leave a Reply

Your email address will not be published.

Harrogate Town
Previous Story

Harrogate Town 0 - 0 Wrexham

Police have issued an urgent appeal to help find a Neil Smith, missing from North Deighton
Next Story

Renewed appeal to find missing North Deighton man